REDEVELOPMENT AND MODERNIZATION SR.11 PADANA SUPERIORE 2 COMPLETION OF THE BYPASS OF PESCHIERA. A SECTION FROM ROVIZZA TO THE TOOL BOOTH OF PECHIERA DEL GARDA
Performance: Operative Supervision
The work, after the Rovizza junction, was parallel to the Milan-Venice railway line; more precisely, the railway line was joined at the progressive Km 1 + 000, at the overpass of the municipal road Lizzara Nuova, up to the Bell’Italia junction at progr. Km 2 + 800 where the overpass to the railway line is foreseen. A second overpass was built in correspondence with the S. Cristina municipal road before entering the delicate area from a geological point of view, the Frassino lake and reaching the Bell’Italia junction which allows you to connect with the existing ring road. The intervention ended with the junction on the current Peschiera ring road at Km 3 + 100.
In the existing section, up to the Peschiera motorway tool, two redevelopment and modernization interventions were carried out at the Ponti S / M junction and the Porto Vecchio junction at the entrance to the new industrial area of Peschiera.